As of September 2017 here is the latest progress report for the soon to be completed Pacific Gate residences:

  • Kitchen cabinetry has been installed up to level 40;
  • Sub-Zero and Miele appliances have been installed up to level 31;
  • Bathroom vanities and tile have been installed up to level 28;
  • Plumbing and electrical fixtures have been installed up to level 23;
  • Hardwood flooring has been installed up to level 24;
  • Final paint has been applied up to level 9;
  • Permanent power to the building began this month;
  • Detailed work in the amenity areas has begun.